HO YIP SHING v. HANDA CONTRACTORS LTD.

HCSD000010/2002

HCSD 10/2002

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

APPLICATION TO SET ASIDE A STATUTORY DEMAND
NO. 10 OF 2002

____________

IN THE MATTER of Ho Yip Shing (何業勝), a debtor

AND

IN THE MATTER of an application to set aside a Statutory Demand under Rule 47 of the Bankruptcy Rules (Chapter 6)

____________

BETWEEN
HO YIP SHING Applicant
AND
HANDA CONTRACTORS LIMITED Respondent

____________

Coram: Hon Kwan J in Chambers

Date of Hearing: 30 April 2002

Date of Decision: 30 April 2002

Date of Handing Down Reasons for Decision: 7 May 2002

_______________________

REASONS FOR DECISION

_______________________

1. This is an application to set aside a statutory demand dated 7 March 2002. The applicant, Ho Yip Shing, was at all material timescarrying on construction works under the name of Sun Cheong Shing Construction & Civil Engineering Works Company. He had signeda contract with the respondent, Handa Contractors Limited, in November 2000 to carry out construction works in relation to the WestKowloon Reclamation Remaining Roadworks Stage 2. The main contractor of the project was Chun Wo Construction & Engineering CompanyLimited (“Chun Wo”). The respondent was the sub-contractor of Chun Wo and the applicant was the sub-sub-contractor. The amount claimedin the statutory demand is HK$236,436.78, being an award made by the Labour Tribunal against the respondent on 9 January 2002 underSection 43G of the Employment Ordinance, Cap.57, by which a superior nominated sub-contractor is obliged to pay the wages of the employees of a nominated sub-contractor.

2. The relevant matters giving rise to this application may be summarised as follows.

3. On 28 May 2001, the respondent obtained an ex parte injunction from the High Court to restrain the applicant from remaining on thesite. Thereafter, the respondent took over the site from the applicant and proceeded to carry out the works. The respondent broughtan action against the applicant in High Court Action No. 2342 of 2001. The Statement of Claim was served on 8 October 2001. It isthe respondent’s case that the applicant was in breach of contract in that he had failed to complete the works by the original dateof 28 January 2001 or by the extended date of 15 April 2001. Further, the work done by the applicant was of poor quality. The respondentis rendered liable to Chun Wo for liquidated damages from 16 April 2001 to 15 July 2001due to the delay in completion of the works.It had incurred expenses in taking over the site, completing the outstanding works and remedying the defective work of the applicant.After deducting the amount due to the applicant for the work done, the respondent claims HK$1,834,406.85 from the applicant for itsloss and damage.

4. The applicant served a defence and counterclaim in the High Court Action on 30 November 2001. He alleged that possession of the sitewas delivered to him on a piecemeal basis, which accounted for the time he took to carry out the works. Further, he was not responsiblefor the prestressing work, which was done by another sub-contractor of Chun Wo. The applicant was required to carry out additionalwork or rectification work by the employer on various occasions because the respondent did not give proper instructions to the applicantin the first place, or because of defective work by the piling sub-contractor and the prestressing sub-contractor of Chun Wo. Dueto the above reasons, the applicant was not liable for the alleged delay and the respondent had wrongfully repudiated its contractwith the applicant by re-entering the site on 28 May 2001. The applicant counterclaims HK$827,304.84, being the balance due to theapplicant for the work done for which he had issued interim payment debit notes in the amount of HK$4,515,843.35 and of which onlyHK$3,688,538.51 was paid by the respondent. He also counterclaims damages to be assessed because of the wrongful termination of hiscontract.

5. The respondent filed a reply and defence to counterclaim on 31 December 2001 denying the applicant’s allegations.

6. In the meantime, eight workers brought a claim in the Labour Tribunal against Chun Wo, the respondent and the applicant in LBTC No.6843 of 2001, claiming that the applicant had failed to pay their wages. On 9 January 2002, a presiding officer made the award thatI have mentioned against Chun Wo and the respondent, jointly and severally, in favour of seven of the claimants. On 1 and 12 March2002, the respondent paid to the Labour Tribunal the total amount of HK$236,436.78 being the award, interest and costs. The statutorydemand was served on the applicant for the said sum on 7 March 2002.

7. It is not in dispute that the amount of HK$236,436.78 paid by the respondent to the applicant’s employees under Section 43G, Cap.57 is a debt due from the applicant to the respondent, as is provided in section 43J(1). The applicant seeks to set aside the statutory demand under rule 48(5)(a) of the Bankruptcy Rules, Cap.6A on the ground that he “appears to have a counterclaim, set-off or cross demand which equals or exceeds the amount of thedebt or debts specified in the statutory demand”, in that he has raised a substantial counterclaim against the respondent in theHigh Court Action in November 2001 in the sum of HK$827,304.84 as stated earlier.

8. The respondent, whilst denying the applicant’s entitlement to the counterclaim in the High Court Action, would appear to have acceptedthat this court cannot resolve the merits or otherwise of the counterclaim at this stage and the matter would have to go to trialin the other action. It was, however, contended by Mr Patrick Tam on behalf of the respondent that the counterclaim in the High CourtAction should not be taken into account because any liability of the respondent to the applicant under the sub-sub-contract was separateand distinct from the applicant’s liability to the respondent by virtue of sections 43G and 43J(1) of Cap.57 and that the demandunder the provisions of Cap.57 was not closely connected with the sub-sub-contract to enable the applicant to put forward a claimfor set-off. He placed reliance on the decision of Jones J in Pysogea v. Rightfairs Development Ltd [1991] 1 HKC 341.

9. Pysogea was concerned with an application to strike out a petition to wind up a company. The company was the sub-contractor to thepetitioner on a construction site and the petitioner was ordered by the Labour Tribunal to pay the arrears of wages, redundancy paymentsand holiday pay of the company’s employees under section 43D of Cap.57. The petitioner having made payment presented a petition towind up the company. There were also proceedings in the High Court brought by the petitioner against the company claiming damagesand other relief for breaches of the sub-contract. The company had served a defence and counterclaim alleging wrongful terminationof the sub-contract. It was contended by the company that the debt claimed in the petition was subject to its right of equitableset-off being its counterclaim in the High Court Action. This contention was rejected by the court. It was held that the sub-contractwas a separate transaction form the liability incurred to the company’s employees under Cap.57 and the demand under the Ordinancewas not closely connected with the sub-contract to enable the company to put forward a claim for equitable set-off.

10. Pysogea was considered by Le Pichon J (as she then was) in Re Finbo Engineering Co Ltd [1998] 2 HKLRD 695, a decision I brought to the attention of the parties. As pointed out in the latter decision, Pysogea was concerned only with equitable set-off, not a right of legal set-off. The difference between the two is that a legal set-off isallowed in respect of debts which are liquidated, even if unconnected, whereas in equity a set-off is permissible for unliquidateddebts provided they are connected. After a comprehensive review of the law, it was held in Re Finbo that at a minimum, it was arguable that the right of legal set-off remains available in Hong Kong, notwithstanding the enactmentof the Application of English Law Ordinance, Cap.88, in 1966. The judge came to the view that the company “plainly” had an arguable defence based on legal set-off to renderthe debt in the winding-up petition “inarguably substantially disputed” on bona fide grounds. The debt in the petition was in respectof a payment made by the petitioner as the superior contractor to the company’s employees under section 43C of Cap.57. The debt whichthe company sought to set-off was the balance of interim payment applications for work done under the sub-contract, being the subjectof the company’s claim against the petitioner in a High Court action.

11. In the present case, the applicant’s counterclaim against the respondent for the balance of interim payment debit notes is clearlya liquidated claim. In view of Re Finbo, it seems to me it is plainly arguable for the applicant to rely on a right of legal set-off as a defence to the debt due to therespondent under the provisions of Cap.57. This is sufficient to dispose of the respondent’s opposition to setting aside the statutorydemand.

12. I should also mention that in opposing the application, the respondent’s counsel has only focussed on set-off. Rule 48(5)(a) of Cap.6Aprovides for “a counterclaim, set-off or cross demand” as instances in which the court may exercise its power to set aside a statutorydemand. A set-off is a monetary cross-claim which is also a defence to the claim made in the action whereas a counterclaim is anycross-claim which is not also a defence (see Hong Kong Civil Procedure, Vol 1, para. 18/17/2). In the instance where a counterclaim is asserted, which equals or exceeds the debt in the statutory demand,the court would have a discretion whether to set aside the statutory demand. The factors to be considered would include the extentof the connection (if any) between the admitted debt in a cross-claim, whether the proceedings in relation to the cross claim arepending or merely contemplated, whether the applicant has been guilty of any delay in seeking to have the cross-claim determined,the age of the admitted debt and the age of the cross-claim, and the nature and extent of any dispute in relation to the cross-claim(see Re Finbo, supra at 703J to 704B).

13. In the present instance, I would also exercise my discretion to set aside the statutory demand on the ground that the applicant appearsto have a counterclaim which exceeds the debt in the statutory demand. As I have stated earlier, the merits of that counterclaimwould have to be determined in the High Court Action. The applicant has not been guilty of delay in pursuing this counterclaim.

14. For the above reasons, I have set aside the statutory demand and awarded costs of the application to the applicant on a gross sumbasis assessed at HK$12,000.00.

(S Kwan)
Judge of the Court of First Instance
High Court

Representation:

Mr William Au, of Messrs William Au & Co., for the Applicant.

Mr Patrick K Y Tam, instructed by Messrs Edmund Cheung & Co., for the Respondent.